Project overview
Location: | Moji ward, Kitakyushu-shi |
User: | Moji port development Co.,Ltd. |
Building type: | Commercial facility |
Building material: | Rebar steel frame |
Number of floor: | 2 floors |
Designer: | Lec Urban Area Research Institute |
Construction area: | Approx. 2,760 m2 |
Total floor area: | Approx. 5,289 m2 |
Completion: | 1999 |
Retrofit: | Apr. 2011 |
Gas type: | Propane |
Product installed
Outdoor unit
Indoor unit
Indoor unit
Precondition
Gas Engine Driven Heat Pump
Aisin recommendation
E1 series retrofit type |
Outdoor unit |
| Stand-alone retrofit type |
| 25HP | AXYGP710E1PE | × | 5 | units |
| 20HP | AXYGP560E1PE | × | 6 | units |
| 16HP | AXYGP450E1PSE | × | 6 | units |
| 13HP | AXYGP355E1PE | × | 2 | units |
| 8HP | AXYGP224E1PE | × | 1 | unit |
| Combined connection retrofit type |
| 25HP | AWYGP710E1PE | × | 1 | unit |
| 20HP | AWYGP560E1PE | × | 2 | units |
| 16HP | AWYGP450E1PE | × | 1 | unit |
Total | | 456 | HP |
Indoor unit |
| Ceiling mounted cassette Round Flow type |
| AXFP160MC | P160 | × | 7 | units |
| AXFP140MC | P140 | × | 31 | units |
| AXFP112MC | P112 | × | 30 | units |
| AXFP90MC | P90 | × | 14 | units |
| AXFP71MC | P71 | × | 13 | units |
| AXFP45MC | P45 | × | 3 | units |
| Ceiling mounted cassette Double Flow type |
| AXCP71M | P71 | × | 1 | unit |
| Ceiling built-in type |
| AXSP140M | P140 | × | 1 | unit |
| Ceiling mounted duct type |
| AXMP140A | P140 | × | 2 | units |
| AXMP90A | P90 | × | 4 | units |
| Ceiling suspended type |
| AXHP112M | P112 | × | 4 | units |
Total | | 110 | units |
Effect after the retrofit with E1 series (example)
-
Comparison of gas consumption
The gas consumption of the model before is regarded as 100.
*Calculated according to actual gas consumption as of July 2010 (before) and July 2011 (after)
User's voice (This is an individual impression. It varies according to installation situation.)
Reason of selection
-
We have been using GHP since we started the business. We considered to replace the GHP as it reached its product longevity.
We considered to adopt EHP as it is easy to maintain, but we selected GHP since it consumes less electricity to avoid electricity demand increase.
-
We selected Aisin GHP for its leading-edge technology with ease of maintenance and to be able to reuse existing refrigeration lines.
Impression
-
We would like to provide "excitement" and make the facility delightful in order to give a good memory to any generation.
GHP contributes to make comfortable environment for the visitors to enjoy our facility timelessly.
-
As entire Japan was required to reduce electricity consumption this summer due to East Japan earthquake in 2011.
Since GHP consumes such a small portion of electricity, we managed to maintain comfortable indoor temperatures while
keeping electricity consumption low. We also managed 36% of gas consumption.
Introduction of user
We, Moji Port Retro Strait Plaza, are contributing to energy saving.
-
We adopted a new character "Banana man Black" as a messenger of ecology and energy saving after East Japan earthquake.
We also appeal for energy saving to visitors with the character.